tasks completed: 2/3 tasks
- put MORE beach sand on site.
- finish filling the pad.
- option - start plastering on the sides of the manual pad.
we started off quite late around 4 because we had to take some sand from 'the beach'. that would definitely be the final trip! so relieved now~~ no more "not enough beach sand". after we got that, then the basic routine starts all over again, MIXING!

the pad is pretty much filled up now. the only thing to do is plastering (smooth out the surface with a mixture of fine sand and cement with some plastering tools).
this is gonna take one more day and the pad will be ready (assuming weather is good to let it dry the next day).
==========================================
CONSTRUCTION DAY 4
tasks: 1 task
BRING SOME BROOMS
we got some cleaning to do...sigh~~(terpaksa yo)
CONSTRUCTION DAY 4
tasks: 1 task
- plastering (we still need to mix)
BRING SOME BROOMS
we got some cleaning to do...sigh~~(terpaksa yo)
starts at 3+pm,